Skip to main content

Moorhen Marsh Phase B- Construction Week of August 20, 2018

Recent work performed:

  • Completed levee reconstruction with geogrid in pond A-2 and A-1.
  • Constructed 3 islands in pond A-2 and began island construction in pond A-1
  • Formed and poured concrete for the boardwalk and viewing platform abutments in pond A-2.
  • Installed timber piles for the boardwalk and viewing platform abutments in pond A-2.
  • Installed 2 water control structures.
  • Began dredging in Peyton Slough.
  • Excavated and installed levee keyways in Fat Slough and began levee reconstruction with geogrid.
  • Began excavating and installing levee keyways in pond B and began levee reconstruction with geogrid on the west side along Peyton Slough.
  • Continued drying and moisture conditioning pond B soils.

Upcoming work:

  • Complete levee reconstruction and island construction in pond A-1.
  • Complete levee reconstruction in Fat Slough.
  • Continue keyway installation and levee reconstruction in pond B.
  • Complete dredging in Peyton Slough.
  • Install the 3 remaining water control structures.
  • Begin installation of the outlet structures to Peyton Slough.
  • Begin installation of rip rap in ponds A-2 and A-1.
  • CCC scheduled for mid September to start constructing the boardwalk and viewing platform.
Join our mailing list